Introduction

Critics often argue that data centers bring large buildings and heavy power demand but few jobs, and on its face the argument is easy to accept.[i] A finished hyperscale campus can run with a relatively small permanent staff.[ii] Yet a count of the people working inside a finished facility captures only a fraction of the sector’s economic footprint. Before a campus opens, electricians, ironworkers, and engineers spend years building it, and specialized manufacturers supply the power and cooling equipment that runs it.[iii] Once it opens, operators buy electricity, maintenance, and security from Iowa businesses and replace servers and other hardware every few years.[iv] That activity matters more in Iowa than in most states. Iowa ranks among the Midwest’s leaders in data center capacity, both in facilities already operating and in projects still in development.[v]

National research finds that counties with data centers see “positive effects on total employment, construction employment, establishments, payroll, tax returns, adjusted gross income, and wages.”[vi] This report estimates how much Iowa employment, income, and output these data center lifecycles support. It first documents the size, location, and development of Iowa’s data center sector. It then estimates the direct investment owners and operators have made to date and have announced for the coming years. Common Sense Institute then uses the Regional Economic Models, Inc. (REMI) Tax-PI+ model to simulate the direct, indirect, and induced effects of two phases of spending—construction and initial equipment, and ongoing operations and equipment replacement. Finally, the report opens the door to future CSI research on the sector’s tax impacts, community investments, and resource demands.

Key Findings

  • Data center owners and operators have invested or announced at least $53 billion in Iowa buildings and equipment through 2031 (table 1).
    • Investments in Iowa data centers to date total an estimated $15.1 billion, or about $4,700 for every Iowan.
    • Announced investments from 2027 through 2031 would add an additional $38.0 billion. At an average of $7.6 billion per year, these direct investments represent roughly 2.8% of Iowa’s current annual GDP.
    • Ongoing operating and replacement spending totaled an estimated $4.4 billion in 2026, and announced projects would add about $10.6 billion a year by 2031.
  • Announced construction and initial equipment purchases would support about 12,775 jobs by 2031, counting direct, indirect, and induced effects.
    • From 2027 through 2031, they would add about $10.4 billion to GDP and $6.3 billion to personal income (table 3).
  • The ongoing operations of Iowa’s data centers produce more sustained jobs and more economic activity than their initial construction.
    • Operations at existing data centers support an estimated 12,647 Iowa jobs in 2026, or nearly three jobs for every direct job (tables 4 and 6).
    • Once operating, announced projects would support about 29,597 jobs in 2031. From 2027 through 2031, they would add about $18.5 billion to GDP and $9.0 billion to personal income (table 4).
  • Job gains reach well beyond technology, to electricians, construction workers, retail workers, teachers, and motor vehicle operators (table 5).
  • Data centers pay more than other employers for the same job titles, from 12% more for security officers to almost 100% more for electrical engineers (figure 4).
    • Average annual pay in the industry that includes data centers reached $125,759 in 2025, nearly double the $63,469 average for all Iowa workers.
  • Relative to its population, Iowa is the Midwest’s data center leader, with more operating capacity per resident than any other state in the region (figure 1).
    • Iowa’s data centers have 71.8 megawatts (MW) of operating capacity per 100,000 residents. Megawatts measure how much electricity a facility can draw at once, which is the most reliable gauge of a data center’s size.
    • Iowa ranks second in the Midwest in total operating capacity (2,324 MW), behind only Ohio. Including planned projects, it ranks fourth in total capacity and second per capita, behind only Indiana.
  • Iowa’s data center sector is on track to more than triple in size by 2031 (table 1).
    • Announced projects would add 5,257 MW to today’s 2,324 MW of operating capacity in about five years. Building what exists today took more than two decades (figure 3).

Iowa’s Data Center Landscape

This section describes Iowa’s data center sector and what its jobs pay. It begins with the size, location, and development of the state’s data center facilities and compares Iowa with the rest of the Midwest. It then compares pay at data centers with pay at other employers.

Iowa’s Data Center Facilities

Figure 1 displays the combined operating and planned data center capacity, measured in megawatts, for each of the 12 Midwest states, ranked from smallest to largest total capacity. Operating capacity—facilities already in service—is shown in blue at the base of each bar. Planned capacity, representing projects in development or under construction, is shown in red above it. Cleanview provides the data.[vii]

Planned capacity figures for all states are a snapshot. Additional projects will likely be announced or finalized in the coming years, which would raise total planned megawatts across the region. At the same time, these figures assume no currently planned projects are canceled or indefinitely delayed.

Figure 1.

Source: Cleanview

Iowa ranks fourth among the 12 Midwest states in combined operating and planned data center capacity, with 7,581 MW. Only Ohio, Indiana, and Illinois rank higher, at 25,759 MW, 16,837 MW, and 9,962 MW, respectively, and all three have much larger economies. Iowa stands out more on operating capacity alone. Its 2,324 MW of capacity already in service ranks second in the Midwest, behind only Ohio’s 4,035 MW and ahead of Illinois at 1,400 MW, Indiana at 1,352 MW, and Nebraska at 1,346 MW. Operating capacity reflects investment already in the ground rather than projects still subject to permitting, financing, or construction timelines.

Iowa’s 5,257 MW pipeline of planned capacity—more than twice its current operating base—points to continued investor interest in the state. Across the Midwest, planned capacity also exceeds operating capacity in most states.

Iowa’s pipeline is large relative to the state’s size, and it builds on a mature operating base. Adjusted for population, Iowa’s operating capacity equals 71.8 MW per 100,000 residents, the highest rate in the Midwest. Nebraska follows at 66.7 MW and North Dakota at 65.8 MW. Iowa’s rate is more than double Ohio’s 33.9 MW.[viii] Iowa’s planned capacity equals 162.3 MW per 100,000 residents, third behind Indiana’s 222.1 MW and Ohio’s 182.5 MW. Combined, Iowa’s 234.1 MW per 100,000 residents ranks second in the region, behind only Indiana’s 241.4 MW. If national demand for AI infrastructure, cloud storage, and digital services continues to grow, Iowa’s operating base and pipeline position the state to compete for a share of new investment.

Figure 2 shows where data center capacity sits within the state. Each bubble represents an individual facility or campus, and bubble size scales with total capacity. Cleanview provides the base data, and CSI supplements it with other public sources where Cleanview lacks coverage.[ix] Because of those supplements, the facilities on the map total roughly 7,936 MW, slightly more than the Cleanview total in figure 1.

Figure 2.

Source: Cleanview, CSI analysis

Iowa’s data center capacity is concentrated in three hubs. The Des Moines metro, which spans Polk, Dallas, Warren, and Madison counties, holds the largest share, with roughly 3,655 MW—or about 46% of mapped capacity. Cedar Rapids and nearby Palo form the state’s second major hub, with roughly 2,792 MW, or 35%. Council Bluffs anchors the western edge of the state with approximately 1,174 MW, or 15%. Together, these three metro areas account for 96% of Iowa’s mapped data center capacity.

A few facilities sit outside the three hubs. Meta has planned a 114 MW campus in Davenport, and Applied Digital has proposed a 200 MW campus near Adair.[x] If built, the Adair County project would be the first large-scale data center campus in Iowa sited outside a metropolitan area.

Capacity and location show where Iowa’s data center sector stands today. They do not, however, show how quickly it got there. Figure 3 traces each campus from the start of development through operation and shows how the sector shifted from a few early facilities to a wave of hyperscale construction.

Figure 3.

Source: Cleanview, CSI analysis

Iowa’s earliest facilities, including the Bluebird Quad Cities site and Google’s first Council Bluffs building, took about two years each to develop. The hyperscale campuses that followed have been built in phases over a decade or more. Google’s Southlands campus and Meta’s Altoona campus have both expanded continuously since the early 2010s, and Microsoft’s Osmium campus has done the same since 2016. Development has also accelerated. Of the 24 campuses in figure 3, 15 began or will begin development in 2020 or later, and 11 of those began or will begin in 2025 or later. Table 9 in Appendix B lists each campus with its operator, county, status, and capacity.

Data Centers Generally Pay Well

Data centers generally pay more than other employers for the same job titles.[xi] Figure 4 compares pay for select job titles at data centers and at other employers in Iowa.

Figure 4.

Source: O*NET, Indeed, Glassdoor, Fedsalary, CareerOneStop, CSI analysis

As figure 4 shows, data centers pay more for every job title in the figure. The pay premium ranges from 12% for security officers, about $5,000 a year, to almost 100% for electrical engineers, about $100,000 a year. For six of the eight titles, data center workers earn at least $40,000 a year more.

As another point of comparison, the Quarterly Census of Employment and Wages reports average annual pay by industry. Data center employees generally fall into the “Computing Infrastructure Providers, Data Processing, Web Hosting, and Related Services” industry. That industry also includes web hosting and data processing firms, so its average pay approximates data center pay rather than measuring it directly. In 2025, the average annual pay for an Iowa worker in this industry was $125,759.[xii] That is nearly double the $63,469 average annual pay for all workers in Iowa.[xiii]

Data Center Economic Activity Explained

Data center spending affects Iowa’s economy in three ways. CSI’s economic model, described in the “Economic Impact Modeling” section, estimates each of them:

  • Direct effects occur at facilities and construction sites. In Iowa, these direct effects include spending on site preparation and construction, buildings and supporting infrastructure, computing and electrical equipment, ongoing facility operations, and wages paid directly to data center employees and contractors.
  • Indirect effects arise when data center operators and construction contractors purchase goods and services from Iowa-based suppliers. These effects include purchases from construction trades, utilities, equipment maintenance providers, telecommunications firms, security companies, professional service firms, and other businesses throughout the supply chain.
  • Induced effects arise when employees of data centers, contractors, and suppliers spend their earnings within Iowa. Household purchases—including housing, food, transportation, health care, retail, and other services—generate additional business activity, employment, and income across the state.

Much of this activity comes from the workers data centers employ, directly or through contractors. During construction, these include ironworkers, electricians, other skilled tradespeople, and professional service providers. Once a facility is operating, they include network engineers, data analysts, janitors, and IT managers. The model also accounts for leakage, the share of spending that flows to suppliers outside Iowa, so the estimates count only activity within the state.

One-time and Ongoing Effects

In addition to distinguishing direct, indirect, and induced effects, the model differentiates between one-time and ongoing effects. One-time effects come from constructing the building and its core power and cooling infrastructure, known as the “warm shell,” and from installing its first servers, computers, and other equipment. Once construction is complete and the servers and equipment are installed, the facility enters the ongoing operations phase, which includes employing a permanent workforce and replacing aging equipment, typically after three to five years, with some equipment taking up to seven years. The model treats operating spending and equipment replacement as annual flows, measured in annual employment, compensation, purchases, value added, and taxes.

One-time and Continued Investment

Data center projects involve two broad kinds of spending. One-time spending covers construction and the initial power, cooling, and computing equipment. Ongoing spending covers operations and the regular replacement of servers and other hardware. This section describes each type of spending included in the economic impact estimates. The cost shares cited here describe typical data center projects nationally, not Iowa projects specifically.

Construction and Development

Electrical infrastructure accounts for roughly 40% to 50% of the construction and development budget, and mechanical and plumbing systems account for another 10% to 20%.[xiv] The remaining budget covers site preparation, foundations, the building shell, interiors, security, and project delivery services.[xv]

Equipment Inside the Building

Data centers require specialized power and cooling equipment, including transformers, generators, uninterruptible power supply and battery systems, chillers, and liquid cooling systems.[xvi] These purchases support specialized manufacturers and technicians who install, commission, and maintain the equipment throughout its life.[xvii]

Ongoing Operations

Operating data centers generate recurring employment and spending on electricity, whose cost varies with its source and the facility’s design; maintenance of cooling, power, and building systems; salaries and benefits for technical, security, and operational staff; network connectivity and bandwidth[xviii]; and software licensing, cybersecurity, and regulatory compliance.[xix] Recurring capital costs also include periodic replacement of servers, storage, and networking equipment, reflected here as amortized hardware refresh.

Additional CapEx After Development

Servers, graphics processing units (GPUs), central processing units (CPUs), and networking equipment represent substantial capital spending, often funded separately by the tenant and potentially exceeding building and infrastructure costs in AI-focused facilities. Hardware replacement cycles of roughly three to five years make this spending recurring.[xx]

Behind-the-Meter Generation and Battery Storage

In power-constrained markets, developers increasingly invest in on-site generation and battery storage to supplement grid supply or bridge connection delays.[xxi] These site-specific investments create additional demand for equipment, infrastructure, specialized construction, permitting, and ongoing operations.[xxii] The model does not count on-site generation and battery storage as direct spending. It captures some of their effect indirectly, through data centers’ demand for electricity, so it may understate the economic activity that behind-the-meter generation and storage support.

Estimated Direct Investment

This section divides data center owners’ direct investment into two phases: Phase 1, construction and development (CapEx)[xxiii], and Phase 2, ongoing operations and equipment refresh (OpEx with CapEx).[xxiv] CSI estimates that owners and operators have invested or announced at least $53 billion in data center construction and development in Iowa, most of it yet to come. These figures are budgeted project costs rather than actual spending, which CSI cannot observe for every owner and operator. CSI considers the $53 billion a minimum because companies generally do not disclose their investments unless state law requires it for a tax incentive. The $53 billion covers buildings and their initial equipment, not ongoing operating costs. The “Data and Methods” subsection explains how CSI built these estimates.

A typical data center construction and development budget breaks down as follows, with each item’s share in parentheses[xxv]:

  • Electrical systems (40% to 50%), including backup power, switchgear, and grid connections.[xxvi]
  • Mechanical cooling systems (around 10% to 20%), including chillers and advanced liquid cooling infrastructure.
  • Interior fit-out finishes (around 10% to 15%), including operational rooms, lobbies, and security areas.
  • Building shell structure (around 10% to 15%), covering the physical building, including external features.
  • Land acquisition (4% to 7%), covering the cost of purchasing the land, including realtor, appraisal, and other real estate-related costs.
  • Fire suppression and security (around 2% to 3%).

In addition to the warm shell construction, which can typically run between $900 million and $1.5 billion per 100 MW facility[xxvii], IT equipment can typically run between $2.5 billion and $4.0 billion per 100 MW facility.[xxviii] These expenditures include servers, storage, and networking equipment. The cost and configuration of data center infrastructure vary widely with facility type, scale, power density, reliability requirements, and computing workload. Large AI-focused facilities represent the high end of the cost range, requiring multibillion-dollar investments and deploying hundreds of thousands of specialized graphics processing units, supported by advanced power, cooling, and networking infrastructure.[xxix] For instance, a single 72-GPU rack can deliver 1,440 petaflops of AI performance.[xxx]

After construction and initial equipping, data center owners and operators begin ongoing operations by employing workers, purchasing energy, and refreshing aging equipment. Recurring costs include the following:

  • Electricity, whose cost varies widely with its source and the data center’s design.
  • Amortized hardware refresh, or recurring capital costs for servers, storage, and networking equipment.
  • Infrastructure maintenance, including preventative maintenance for cooling, power, and building systems.
  • Personnel, including salaries and benefits for technical, security, and operational staff.
  • Network and bandwidth.
  • Software, security, and compliance, including software licensing, cybersecurity, and regulatory compliance.

The next subsection explains how CSI applied these cost categories to Iowa’s historical and announced projects to estimate direct investment.

Data and Methods

Estimating the direct impact of data centers requires three pieces of information:

  • Historical investment and capacity to date.
  • Known, announced future investment and capacity.
  • A reasonable projection of future investment and capacity not yet announced. This report does not address unannounced future investment.[xxxi]

CSI gathered published information on each project’s capacity, square footage, operational years, project costs, direct jobs, annual wages, completion date where available, and Iowa Economic Development Authority contract number. Sources include the Iowa Economic Development Authority, Cleanview, Aterio, and other public records. Where information was missing, CSI imputed it from the project costs, square footage, and capacity of comparable projects.

CSI then sorted projects into historical and known projected categories. This step accounts for the timing of investment and allows CSI to estimate capacity utilization, which drives electricity costs.[xxxii]

After deriving these overall, one-time construction and equipping costs, CSI built a separate estimate for ongoing operations and equipment replacement. The model assumes data centers operate at 40% of their total MW capacity.[xxxiii] That assumption drives the electricity estimates. CSI then estimated operating spending using spending-category estimates from Dr. Vila at Alpha Matica.[xxxiv] For employment and wages, the model uses estimates from a Decision Innovation Solutions study for the Technology Association of Iowa.[xxxv] CSI checked those estimates against Iowa Economic Development Authority incentive contracts and the federal Quarterly Census of Employment and Wages.

Table 1 shows the resulting estimates for each period: one-time project costs to construct and equip data center buildings, annual ongoing spending in the final year of the period, and capacity.

Table 1. Direct Data Center Investment and Capacity by Period

Period One-time Project Cost (Budgeted) Annual Ongoing Spending, Final Year of Period Capacity
Historical, 2011–2026 $15.1 billion $4.4 billion 2,324 MW
Known Projected, 2027–2031 $38.0 billion $10.6 billion 5,257 MW

Source: CSI analysis
Note: Ongoing spending includes wages, electricity, hardware refresh, infrastructure maintenance, network, software, and security. Known projected figures cover announced projects only, not facilities already operating.

From 2011 through 2026, owners and operators invested $15.1 billion in data center buildings and equipment in Iowa and built about 2,324 MW of capacity. That amounts to $4,662 invested per Iowan. Announced projects would add $38.0 billion—or $11,734 per Iowan—and 5,257 MW from 2027 to 2031. The announced investments would more than double the historical totals in about a third of the time. Put differently, Iowa’s data center sector is on track to more than triple in size by 2031.

For scale, Iowa’s economy produced about $272 billion in goods and services in 2025.[xxxvi] The $38 billion in announced investment averages about $7.6 billion a year from 2027 through 2031, or roughly 2.8% of Iowa’s 2025 GDP each year. One-time spending captures only part of the picture. Ongoing operating and replacement spending at existing facilities totals an estimated $4.4 billion in 2026. Once operating, announced projects would add about $10.6 billion a year by 2031, for a combined total of roughly $15 billion if existing facilities continue at their current level. At the 40% utilization rate the model assumes, the newly announced capacity would use roughly 18 million megawatt-hours of electricity per year, or about one-third of Iowa’s total retail electricity sales in 2024.[xxxvii]

Table 2 breaks the one-time and ongoing totals into detailed spending categories using published cost-structure estimates.

Table 2.

Source: CSI analysis
Note: Construction and development includes construction, development, and first-time equipment. Ongoing operations include personnel, equipment replacement, and maintenance.

As table 2 shows, equipment accounts for nearly three-quarters of one-time investment in both periods—$11.0 billion of the historical $15.1 billion and $27.7 billion of the projected $38.0 billion. Hardware refresh makes up about two-thirds of annual operating expenditures, followed by electricity and personnel. That spending supports electricians, construction workers, attorneys, architects, engineers, IT professionals, and many other workers. Appendix A provides further details behind these figures.

Economic Impact Modeling

The model takes the direct investment described in the previous section as its starting point: at least $53 billion in one-time construction and equipment spending, plus billions of dollars a year in ongoing operations. Companies are already investing over $4 billion a year to operate Iowa’s existing data centers. These investments have spillover effects on the broader economy. Appendix A details the modeling.

The investment figures presented so far are historical or announced. CSI’s modeling tool, REMI Tax-PI+ version 7125, projects future effects; it is not designed to model historical ones. Past investment still had dynamic economic effects, even if modeling them is imperfect. The historical results therefore estimate what Iowa would gain if it saw roughly the same data center development over the next 10 years as it did from 2011 through 2026. They indicate the order of magnitude of that investment’s impact, not a precise measure of past effects. In practice, the model spreads estimated one-time investment from 2011 through 2026 evenly across 2027 through 2036 and ramps up ongoing spending over those years, as Appendix A explains. For simplicity, the dollar figures are reported in nominal terms.

The “Data Center Economic Activity Explained” section describes how direct spending generates indirect and induced effects. This section presents those effects in two phases: Phase 1 covers construction and initial equipment, and Phase 2 covers ongoing operations and equipment refresh. The last two subsections show which occupations gain jobs and how the effects divide among direct, indirect, and induced activity. Throughout, job figures reflect a single year or annual averages as noted; other measures are cumulative over the modeled period. All measures follow REMI’s definitions: business sales are the total value of goods and services Iowa businesses sell; GDP is value added, or sales minus the cost of purchased inputs; personal income is the income Iowa residents receive; and disposable personal income is personal income after taxes. Because GDP is a portion of business sales, the two should not be added together.

Phase 1: Construction and Initial Equipment

Table 3 shows the modeled effects of one-time construction and equipment spending. Using REMI’s forward-looking modeling to approximate the historical experience from 2011 through 2026,[xxxviii] the buildout of the warm shell of data centers and the first-time purchase of equipment produces the following modeled effects. Jobs are for the final modeled year, and the other measures are cumulative over the 10 modeled years:

  • About 1,873 jobs in 2026.
  • Cumulative sales of Iowa-based businesses of $7.3 billion.
  • A boost to cumulative gross domestic product (GDP) of approximately $4.0 billion.
  • A rise in cumulative personal income of about $2.6 billion.
  • An increase in cumulative disposable personal income of about $2.3 billion.

Looking forward, known projected investments announced to date would produce the following impacts from 2027 through 2031:

  • About 12,775 jobs in 2031.
  • Cumulative sales of Iowa-based businesses of $18.8 billion.
  • A boost to cumulative GDP of approximately $10.4 billion.
  • A rise in cumulative personal income of about $6.3 billion.
  • An increase in cumulative disposable personal income of about $5.6 billion.

Table 3.

Source: REMI, CSI analysis
Note: This analysis includes the results of the direct spending on warm shell building, electrical systems, mechanical cooling systems, interior fit-out, building shell structure, commissions on land acquisition, fire suppression and security, and equipment for inside the data center.

Table 3 shows how these one-time effects build over the modeled years. The historical buildout supports about 2,383 average annual jobs each year, while the projected future buildout of data centers would support an estimated 13,354 average annual jobs from 2027 to 2031. In their final modeled years, the effects of the projected future buildout are nearly seven times larger, while average annual jobs are nearly six times larger. Announced investment is about 2.5 times the historical total, and the model concentrates it in five years rather than spreading it over 10. The one-time effects are modest relative to the investment because most of it buys servers and other equipment made outside Iowa. The $15.1 billion historical buildout generates about $7.3 billion in Iowa business sales and $4.0 billion in GDP. The $38.0 billion projected buildout generates about $18.8 billion and $10.4 billion, respectively.

Phase 2: Ongoing Operations and Equipment Refresh

Once operational[xxxix], data centers produce ongoing employment and income effects. Using the same approach as Phase 1, ongoing operations and equipment refresh at Iowa’s existing data centers produce the following modeled effects, shown in table 4. Jobs are for the final modeled year, and the other measures are cumulative over the 10 modeled years:

  • About 12,647 jobs in 2026.
  • Cumulative sales of Iowa-based businesses of $30.3 billion.
  • A boost to cumulative GDP of approximately $17.0 billion.
  • A rise in cumulative personal income of about $8.6 billion.
  • An increase in cumulative disposable personal income of about $7.6 billion.

Looking forward, known projected investments announced to date would produce the following impacts from 2027 through 2031:

  • About 29,597 jobs in 2031.
  • Cumulative sales of Iowa-based businesses of $33.0 billion.
  • A boost to cumulative GDP of approximately $18.5 billion.
  • A rise in cumulative personal income of about $9.0 billion.
  • An increase in cumulative disposable personal income of about $7.9 billion.

Table 4.

Source: REMI, CSI analysis
Note: This analysis includes the direct employment of data centers, purchases from electricity providers, amortized hardware purchases (virtually all from out of state), infrastructure maintenance, network and bandwidth purchases, and software/security compliance spending.

As table 4 shows, ongoing operations account for most of the modeled impact. In the final modeled year, operations of existing data centers support about 12,647 jobs, roughly five times the 2,383 average annual jobs supported by the historical construction buildout. Over the 10 modeled years, operations add about $17.0 billion to GDP, over four times the $4.0 billion from the construction buildout. Once operating, announced projects would support another 29,597 jobs by 2031.

Job Gains Are Broad Based

Data centers directly employ analysts, IT technicians, and other information-related professionals. Across the full investment pipeline, however, these jobs are only a fraction of the total employment impact. Table 5 lists the occupations with the most jobs in the final modeled year of each period, combining construction and ongoing operations. Building data centers and keeping them maintained supports jobs for electricians, ironworkers, construction laborers, engineers, and many other occupations.

Table 5.

 

Source: REMI, CSI analysis
Note: The jobs are for the final year of the relevant period.

As table 5 shows, data center construction and operations affect far more than technology companies and information analysts. Spending by data center builders and operators reaches electricians, retail workers, teachers, construction workers, material moving workers, motor vehicle operators, and a host of other employees who make Iowa’s economy move. These effects span many sectors and, because operations continue after construction ends, they persist beyond the buildout.

Direct, Indirect, and Induced Effects

Economic impact analysis distinguishes three types of effects: direct, indirect, and induced. In this report, direct impacts include purchases by companies that build data centers and companies that occupy and use them. Direct ongoing jobs reach beyond on-site data center staff: the model’s 4,447 direct jobs in 2026 compare with about 3,550 jobs that federal employment data assign to the main data center industry classification.[xl] Supplier activity generated by those purchases is the indirect impact, and spending from workers’ household income is the induced impact. Table 6 shows the direct, indirect, and induced economic effects for the one-time construction and development expenditures and the ongoing operations in the final modeled year of each period—2026 for the historical scenario and 2031 for the known projected scenario. These totals match the final-year columns of tables 3 and 4, not the period averages those tables also report. Appendix A describes how CSI calculated these effects.

Table 6. Direct, Indirect, and Induced Economic Impact

Source: REMI, CSI analysis

Table 6 shows that the two phases produce their effects in different ways. Direct activity accounts for about half or more of the one-time construction jobs in both periods: 1,091 of 1,873 in 2026 and 6,365 of 12,775 in 2031. For ongoing operations, induced effects account for most of the jobs, about 64% in 2026 (8,092 of 12,647) and 62% in 2031 (18,314 of 29,597). Indirect effects are small in both phases and account for less than 1% of operations jobs. Household spending tied to data center activity is therefore the largest source of modeled jobs in both periods.

Future Research

Data centers affect their host communities in ways the economic impact estimates do not capture. This section describes the voluntary investments operators make in those communities, the electricity and water the facilities require, and the local taxes they pay. The modeling in the previous section does not include these effects. These topics merit additional research.

Community Investments

Data centers invest in their communities through water conservation, development of rural trails, donations to schools for STEM education, grants to nonprofit organizations, and other investments in local quality of life. These investments can make a location more attractive, but this report does not analyze them. Examples from data center operators include the following:

  • Google committed $1.3 million to water conservation in the Missouri River valley.[xli]
  • Meta’s Altoona Data Center gave the Science Center of Iowa a $15,000 grant for teacher training and student summer camps.[xlii]
  • Meta supported access points to the ICON Water Trails system in Altoona and Bondurant.[xliii]
  • Amazon committed to job training and water and energy conservation.[xliv]

These community contributions are acknowledged here but are not quantified in this study’s economic impact estimates.

Resource Stewardship

Data centers require electricity to power IT equipment and supporting infrastructure, and Iowa’s pipeline is large relative to the state’s grid. In 2024, Iowa used electricity at an average rate of roughly 6,250 MW.[xlv] At the 40% utilization this report assumes, the 7,581 MW of operating and planned data center capacity described earlier would draw roughly 3,000 MW on average, or nearly half of the state’s 2024 average load. Because utilities must plan for peak demand rather than average use, Iowa’s utilities are adding new generation to meet that demand.

Alliant Energy expects demand on its system to rise 60% by 2031 under signed agreements with large-load customers such as data centers.[xlvi] To serve that growth, it has filed for the 720 MW Morgan Valley and 1,200 MW Riverhawk natural gas plants, along with roughly 125 MW of battery storage.[xlvii] MidAmerican Energy has proposed the Orient Energy Center, a natural gas plant in Adair County that would generate up to 700 MW during periods of peak demand.[xlviii] That load growth can also benefit other ratepayers. In an August 5, 2026, release, the International Transmission Company (ITC) Midwest announced, “ITC Midwest’s network transmission rate is expected to decrease by approximately 20% by 2030, demonstrating how load growth can deliver long-term cost benefits for customers.”[xlix] Network demand driven largely by data centers in Cedar Rapids fueled load growth that led to the anticipated rate reductions, according to the release.

On-site water needs also vary with cooling technology, workload, and local conditions. Lawrence Berkeley National Laboratory projects that U.S. hyperscale data centers will consume between 60 and 124 billion liters of water in 2028.[l] These resource demands are important considerations alongside the economic impacts examined here, and CSI will examine data center energy and water use in greater depth in a future report.

Local Tax Contributions

Beyond voluntary contributions, data centers add to the resources available to their host communities through the taxes they pay. Most of Iowa’s campuses sit on land that was farmed until construction began, and developing that land into data centers adds substantial value to local tax rolls. That added value generates property tax revenue that local governments can use to fund schools and other public services, to lower property tax rates for residents and businesses, or to do some of both. Increased activity around these campuses may also support local commerce and the sales tax revenue it generates. CSI will examine data center property taxes, their effect on local levy rates, and Iowa’s sales tax treatment of data center equipment in greater depth in a forthcoming report.

Bottom Line

Data centers support far more economic activity in Iowa than their permanent on-site workforce suggests. Owners and operators have already invested billions of dollars in Iowa data center buildings and equipment, and announced projects would add more than twice that amount. The spending reaches construction trades, utilities, maintenance contractors, and service providers, along with the households those workers support. CSI’s modeling shows that ongoing operations and equipment replacement sustain thousands of Iowa jobs year after year, long after construction crews leave. Because announced projects more than double the investment made to date, much of the sector’s economic impact in Iowa still lies ahead.

That growth has implications for policy. Decisions on power generation, transmission, permitting, and tax treatment shape where data centers locate. Policymakers weighing such decisions can measure their effects against the sector’s full lifecycle of construction, operations, and equipment replacement rather than the permanent jobs inside each building. The same pipeline that makes data centers a source of growth also brings real demands. At the utilization this report assumes, operating and planned data centers would draw nearly half of Iowa’s 2024 average electricity load. If policymakers want to keep attracting this investment, the state’s ability to meet that demand will weigh heavily in where the next projects go. Future CSI research will examine the sector’s tax impacts, community investments, and resource demands in greater depth.

Appendix A: Dynamic Economic Impact Modeling Assumptions, Historical (2011–2026) and Known Projections (2027–2031)

To model the dynamic economic impact of data center investment in Iowa, CSI used the following assumptions for the construction and development phase and for the ongoing operations and equipment refresh phase. Because the modeling software cannot model past years, the model projects 10 years ahead rather than reconstructing the historical impact. The historical results therefore estimate the effects of the next 10 years of data center development based on observed data from 2011 through 2026. To fit 16 years of construction, development, and growing ongoing spending into the model, CSI divided the total one-time construction spending from 2011 through 2026 by 10 and entered that amount in each modeled year, so the model runs the full historical buildout. Ongoing spending grows each year, starting at one-tenth of its final-year level for the historical path and one-fifth for the known projected path.

Estimated Historical, 2011–2026

Table 7.

Source: CSI analysis

Known Projected, 2027–2031

Table 8. Direct, Indirect, and Induced Estimates

 

Source: CSI analysis

For the one-time construction and development impact, the model uses REMI’s direct, indirect, and induced estimates. For the ongoing impact, it uses REMI’s indirect estimate and CSI’s own estimate of direct jobs, and it calculates induced jobs as total jobs minus direct and indirect jobs. CSI then applies those job shares to the ongoing output impact to split it into direct and indirect output, with induced output as the remainder.

Appendix B: Iowa’s Data Center Campuses

Table 9.

Source: Cleanview, CSI analysis
Note: *Apple has not disclosed the planned capacity of its Waukee campus, so the figure shown is a third‑party estimate from Server Country. **Meta has not disclosed the planned capacity of its Davenport campus, so the figure shown is a third‑party estimate from Server Country.

Endnotes

[i] Dany Bahar and Greg Wright, “New evidence on data center employment effects,” Global Economy and Development, Brookings Institution, May 4, 2026, https://www.brookings.edu/articles/new-evidence-on-data-center-employment-effects/.

[ii] Dany Bahar and Greg Wright, “New evidence on data center employment effects,” Global Economy and Development, Brookings Institution, May 4, 2026, https://www.brookings.edu/articles/new-evidence-on-data-center-employment-effects/; “IEDA Board approves assistance for established company, two startups in Iowa,” Iowa Economic Development Authority, May 17, 2024, https://opportunityiowa.gov/press-release/2024-05-17/ieda-board-approves-assistance-established-company-two-startups-iowa.

[iii] Navin Girishankar and Karl Smith, “GenAI’s Human Infrastructure Challenge—Can the United States Meet Skilled Trade Labor Demand Through 2030?,” Center for Strategic & International Studies, September 15, 2025, https://www.csis.org/analysis/genais-human-infrastructure-challenge-can-united-states-meet-skilled-trade-labor-demand; Didier Vila, PhD, “Deconstructing the Data Center: A Look at the Cost Structure,” Alpha Matica, Accessed September 2026, https://www.alpha-matica.com/post/deconstructing-the-data-center-a-look-at-the-cost-structure-1.

[iv] “Form 10-K for the Fiscal Year Ended December 31, 2025,” Digital Realty Trust, Inc., U.S. Securities and Exchange Commission, February 13, 2026, https://www.sec.gov/Archives/edgar/data/1494877/000110465926015365/dlr-20251231x10k.htm; “Data Centers and Telecommunications Facilities,” 2023 ASHRAE Handbook—HVAC Applications, ASHRAE, 2023, https://www.ashrae.org/technical-resources/ashrae-handbook.

[v] “Data Centers in Iowa — Project List & Locations,” Cleanview, Accessed October 2026, https://cleanview.co/data-centers/iowa; CSI analysis.

[vi] Fernando E. Alvarez, David Argente, Joyce Chow, and Diana Van Patten, “Data Centers and Local Economies in the Age of AI: A Shift–Share Approach,” Working Paper No. 2026-67, Becker Friedman Institute for Economics, University of Chicago, May 2026, https://bfi.uchicago.edu/wp-content/uploads/2026/05/BFI_WP_2026-67.pdf.

[vii] “Free Data Center Tracker Tool,” Cleanview, Accessed September 2026, https://cleanview.co/data-centers

[viii] “Annual Estimates of the Resident Population for the United States, Regions, States, District of Columbia, and Puerto Rico (NST-EST2025-POP),” U.S. Census Bureau, U.S. Department of Commerce, Accessed October 2026, https://www.census.gov/data/tables/time-series/demo/popest/2020s-state-total.html; https://cleanview.co/data-centers/iowa.

[ix] “Data Centers in Iowa ,” Cleanview, accessed September 2026, https://cleanview.co/data-centers/iowa; “Iowa Data Centers Inventory,” Aterio, Accessed September 2026, https://www.aterio.io/insights/us-data-centers/ia.

[x] “IEDA Board approves assistance for established company, two startups in Iowa,” Iowa Economic Development Authority, May 17, 2024, https://opportunityiowa.gov/press-release/2024-05-17/ieda-board-approves-assistance-established-company-two-startups-iowa; “Regular Session Minutes,” Board of Supervisors, Adair County, April 2, 2024, https://www.adaircounty.iowa.gov/files/meetings/2024-04-02_minutes_4647.pdf; “Data Centers in Iowa,” Cleanview, Accessed October 2026, https://cleanview.co/data-centers/iowa.

[xi] Aubrey Woessner and Laura Ullrich, “Working in the Data Center Build-Out,” Hiring Lab, Indeed, August 13, 2026, https://hiringlab.indeed.com/2026/08/13/working-in-the-data-center-build-out/.

[xii] “Quarterly Census of Employment and Wages, Data Views,” U.S. Bureau of Labor Statistics, U.S. Department of Labor, Accessed September 2026, https://data.bls.gov/cew/apps/data_views/data_views.htm#tab=Tables.

[xiii] “Quarterly Census of Employment and Wages, Data Views.”

[xiv] Vinish Bawa, Brian Burns, Clara Cutajar, Jens Niebuhr, Danny Touma and CB Velayuthan, “Where $31.6 trillion of capex flows in the era-defining AI build-out,” PwC, September 2, 2026,

https://www.pwc.com/gx/en/1/services/consulting/technology/data-centre-outlook.html; “The capex crucible: What finance teams can learn from data center builds,” McKinsey & Company, February 18, 2026, https://www.mckinsey.com/capabilities/strategy-and-corporate-finance/our-insights/the-capex-crucible-what-finance-teams-can-learn-from-data-center-builds; Navin Girishankar and Karl Smith, “GenAI’s Human Infrastructure Challenge—Can the United States Meet Skilled Trade Labor Demand Through 2030?,” Center for Strategic & International Studies, September 15, 2025, https://www.csis.org/analysis/genais-human-infrastructure-challenge-can-united-states-meet-skilled-trade-labor-demand; Didier Vila, PhD, “Deconstructing the Data Center: A Look at the Cost Structure,” Alpha Matica, Accessed September 2026, https://www.alpha-matica.com/post/deconstructing-the-data-center-a-look-at-the-cost-structure-1, and CSI research and analysis.

[xv] Didier Vila, PhD, “Deconstructing the Data Center: A Look at the Cost Structure,” Alpha Matica, Accessed September 2026, https://www.alpha-matica.com/post/deconstructing-the-data-center-a-look-at-the-cost-structure-1; CSI research and analysis.

[xvi] Didier Vila, PhD, “Deconstructing the Data Center: A Look at the Cost Structure,” Alpha Matica, Accessed September 2026, https://www.alpha-matica.com/post/deconstructing-the-data-center-a-look-at-the-cost-structure-1; CSI research and analysis.

[xvii] Didier Vila, PhD, “Deconstructing the Data Center: A Look at the Cost Structure,” Alpha Matica, Accessed September 2026, https://www.alpha-matica.com/post/deconstructing-the-data-center-a-look-at-the-cost-structure-1; CSI research and analysis.

[xviii] “Cooling Water Efficiency Opportunities for Federal Data Centers,” United States Department of Energy, Accessed September 2026, https://www.energy.gov/cmei/femp/cooling-water-efficiency-opportunities-federal-data-centers; “Data Centers in Virginia, 2024,” Joint Legislative Audit and Review Commission, Commonwealth of Virginia, December 9, 2024, https://www.appomattoxcountyva.gov/DocumentCenter/View/768/JLARC-Data-Center-Study?bidId=; “Management and Operations Guideline,” Uptime Institute, Accessed September 2026, https://uptimeinstitute.com/professional-services/management-operations/mando-criteria; “Form 10-Q for the Quarterly Period Ended June 30, 2026,” Equinix, Inc., U.S. Securities and Exchange Commission, July 2026, https://investor.equinix.com/sec-filings/all-sec-filings/content/0001101239-26-000147/eqix-20260630.htm; “Walsh Data Center Initial Study and Proposed Mitigated Negative Declaration,” Siting, Transmission and Environmental Protection Division, California Energy Commission, February 2020, https://files.ceqanet.lci.ca.gov/259363-2/attachment/agW7OFEjD111eMa2a-2bulWi_pGeVksUxCXri4w6rUDo-hSXz52T1nULVowDYvuZlFVx6dU5jxO6pnQr0.

[xix] “Form 10-K for the Fiscal Year Ended December 31, 2025,” Digital Realty Trust, Inc., U.S. Securities and Exchange Commission, February 13, 2026, https://www.sec.gov/Archives/edgar/data/1494877/000110465926015365/dlr-20251231x10k.htm.

[xx] “The cost of compute: A $7 trillion race to scale data centers,” McKinsey Quarterly, McKinsey & Company, April 28, 2025, https://www.mckinsey.com/industries/technology-media-and-telecommunications/our-insights/the-cost-of-compute-a-7-trillion-dollar-race-to-scale-data-centers; “2026 Annual Review, Notice of Annual Meeting, Proxy Statement, and Form 10-K,” NVIDIA Corporation, May 12, 2026, https://s201.q4cdn.com/141608511/files/doc_financials/2026/ar/2026-annual-report-web-Hyperlinks.pdf; “Data Centers in Virginia, 2024,” Joint Legislative Audit and Review Commission, Commonwealth of Virginia, December 9, 2024, https://www.appomattoxcountyva.gov/DocumentCenter/View/768/JLARC-Data-Center-Study?bidId=; Didier Vila, PhD, “Deconstructing the Data Center: A Look at the Cost Structure,” Alpha Matica, Accessed September 2026, https://www.alpha-matica.com/post/deconstructing-the-data-center-a-look-at-the-cost-structure-1; “Data Centers and Telecommunications Facilities,” Chapter 20, 2023 ASHRAE Handbook—HVAC Applications, ASHRAE, 2023, https://www.ashrae.org/technical-resources/ashrae-handbook. Note: ASHRAE describes the typical life cycle of data center IT equipment as three to five years.

[xxi] “Key Questions on Energy and AI,” World Energy Outlook Special Report, International Energy Agency, April 16, 2026, https://iea.blob.core.windows.net/assets/3179f7f8-01f6-4dd6-bffa-c9f7b73f1dc9/KeyQuestionsonEnergyandAI.pdf#page=51; “GE Vernova and Crusoe announce major 29-unit aeroderivative gas turbine deal to deliver power to AI data centers,” Crusoe, July 22, 2025, https://www.crusoe.ai/resources/newsroom/ge-vernova-and-crusoe-announce-major-29-unit-gas-turbine-deal.

[xxii] Paul W. Parfomak, Ashley J. Lawson, Martin C. Offutt, and Ling Zhu, “Data Center Energy Infrastructure: Federal Permit Requirements,” R48762, Congressional Research Service, 2026, https://www.congress.gov/crs_external_products/R/PDF/R48762/R48762.2.pdf; “Solar-Plus-Storage 101,” Integrated Energy Systems Office, U.S. Department of Energy, March 11, 2019, https://www.energy.gov/cmei/systems/articles/solar-plus-storage-101.

[xxiii] CapEx refers to capital expenditures, which are typically one-time expenses for, in this report, constructing the warm shell of the building, customizing the building for use by data center users, and filling the space with servers, cooling equipment, and other equipment used in the digital infrastructure world.

[xxiv] The ongoing phase includes OpEx—which are operating expenditures for running the data center, comprising such investments as payroll employment, electrical maintenance, and purchases from energy suppliers—and CapEx. The ongoing phase includes CapEx because the expensive equipment inside the warm shell building wears out and needs to typically be replaced every five to seven years (of course, the economic life of the various types of equipment varies widely by the type of equipment and business practices of the companies paying for the equipment refresh).

[xxv] Didier Vila, PhD, “Deconstructing the Data Center: A Look at the Cost Structure,” Alpha Matica, Accessed September 2026, https://www.alpha-matica.com/post/deconstructing-the-data-center-a-look-at-the-cost-structure-1.

[xxvi] In some cases, data centers supplement grid electricity with behind-the-meter generation and battery storage. Completely off-grid data centers are uncommon.

[xxvii] Didier Vila, PhD, “Deconstructing the Data Center: A Look at the Cost Structure,” Alpha Matica, Accessed September 2026, https://www.alpha-matica.com/post/deconstructing-the-data-center-a-look-at-the-cost-structure-1.

[xxviii] Didier Vila, PhD, “Deconstructing the Data Center: A Look at the Cost Structure,” Alpha Matica, Accessed September 2026, https://www.alpha-matica.com/post/deconstructing-the-data-center-a-look-at-the-cost-structure-1.

[xxix] Sarah Smith, Alexander Hubbard, et al., “United States Data Center Energy Usage Report: 2025 Update,” Lawrence Berkeley National Laboratory, 2026,  https://datacenters.lbl.gov/resources/total-cost-ownership-tco-model-data; Scott Guthrie, “Infinite scale: The architecture behind the Azure AI superfactory,” Microsoft, November 12, 2025, https://blogs.microsoft.com/blog/2025/11/12/infinite-scale-the-architecture-behind-the-azure-ai-superfactory/.

[xxx] Rani Borkar and Nidhi Chappell, “Microsoft Azure delivers the first large scale cluster with NVIDIA GB300 NVL72 for OpenAI workloads,” Microsoft, October 9, 2025, https://azure.microsoft.com/en-us/blog/microsoft-azure-delivers-the-first-large-scale-cluster-with-nvidia-gb300-nvl72-for-openai-workloads/.

[xxxi] Global Data Centre Outlook 2026–50 (PwC, September 2026), https://www.pwc.com/gx/en/1/services/consulting/technology/data-centre-outlook.html. Although unannounced investments are not part of this report, Iowa is an attractive location for future data center investment. One recent forecast projects that global data center capital expenditures will grow from roughly $800 billion in 2026 to $1.8 trillion per year by 2050, for a cumulative total of $31.6 trillion. The United States is expected to capture about 48 percent of that total, or $15.1 trillion. If Iowa were to attract just 2 percent of projected U.S. investment, data center companies would invest about $302 billion in physical infrastructure in the state. That figure covers only capital expenditures. Companies would also employ Iowans to run the data centers and buy energy from Iowa-based suppliers.

[xxxii] If the investment and capacity figures are not carefully accounted for across time, one will arrive at implausible results on, for instance, electricity usage.

[xxxiii] “Data Center Load Growth in Context,” Powering Intelligence, EPRI, February 21, 2026, https://powering-intelligence.epri.com/load-growth.html. Note: Plausible range estimates for operating capacity are between 30% and 70%. This study uses 40% based upon the EPRI research of energy consumption of data centers.

[xxxiv] Didier Vila, PhD, “Deconstructing the Data Center: A Look at the Cost Structure,” Alpha Matica, Accessed September 2026, https://www.alpha-matica.com/post/deconstructing-the-data-center-a-look-at-the-cost-structure-1.

[xxxv] “Economic Impact Study of Data Centers in Iowa,” Decision Innovation Solutions, January 2026, https://www.technologyiowa.org/wp-content/uploads/2026/03/Economic-Impact-Data-Centers-Iowa-TAI-optimized.pdf#page=15.

[xxxvi] “SAGDP2 Gross Domestic Product (GDP) by State,” U.S. Bureau of Economic Analysis, U.S. Department of Commerce, Accessed October 2026, https://apps.bea.gov/itable/?ReqID=70.

[xxxvii] “Iowa Electricity Profile 2024,” U.S. Energy Information Administration, November 10, 2025, https://www.eia.gov/electricity/state/iowa/.

[xxxviii] Just a reminder: the historical lookback was modeled as if the historical experience happened again over the coming 10 years. That is why the table reports 2011 and 2026.

[xxxix] Just a reminder: the historical lookback was modeled as if the historical experience happened over the coming 10 years. That is why the table reports 2011 and 2026.

[xl] U.S. Bureau of Labor Statistics, Quarterly Census of Employment and Wages, 2025 annual averages, NAICS 518210, “Computing Infrastructure Providers, Data Processing, Web Hosting, and Related Services,” accessed October 14, 2026, QCEW Data Files.

[xli] Jackson Piercy, “Google investing another $1 billion into Council Bluffs data center,” WOWT, July 2, 2024, https://www.wowt.com/2024/07/02/google-investing-another-1-billion-into-council-bluffs-data-center/.

[xlii] “Science Center of Iowa awarded $15,000 grant from Meta Altoona Data Center,” Science Center of Iowa, March 29, 2023, https://www.sciowa.org/about-sci/media-center/news-releases/science-center-of-iowa-awarded-15-000-grant-from-meta-altoona-data-center/.

[xliii] “Meta Announces New Expansion to Altoona Campus + New Hardhat in Hand Graduates,” Meta, December 14, 2021, https://datacenters.atmeta.com/2021/12/meta-announces-new-expansion-to-altoona-campus-new-hardhat-in-hand-graduates/.

[xliv] Anne D’Innocenzio, “Amazon to invest $1B into data center communities amid backlash against data center rollouts,” Associated Press, October 2, 2026, https://apnews.com/article/amazon-data-centers-1-billion-investment-91b65ba1729540c1c0d92e35deef35d8.

[xlv] “Iowa Electricity Profile 2024.”

[xlvi] “Alliant Energy Announces Second Quarter 2026 Results,” Alliant Energy Corporation, July 30, 2026, https://www.businesswire.com/news/home/20260730811350/en/.

[xlvii] “Q2 2026 Earnings Call,” Alliant Energy Corporation, July 31, 2026, https://s201.q4cdn.com/991130938/files/doc_financials/2026/q2/2026-Q2-Earnings-Call-Slides-FINAL.pdf.

[xlviii] “Orient Energy Center Simple-Cycle Combustion Turbine Project,” MidAmerican Energy Company, Accessed October 2026, https://midamericanenergy.com/media/pdf/orient_energy_center_fact_sheet.pdf.

[xlix] “U.S. Energy Secretary Visits Cedar Rapids,” ITC Midwest, ITC Holdings Corp., August 5, 2026, https://www.itc-holdings.com/?p=32895.

[l] Sarah Smith, Alexander Hubbard, et al., “United States Data Center Energy Usage Report: 2025 Update,” Lawrence Berkeley National Laboratory, 2026,  https://datacenters.lbl.gov/resources/total-cost-ownership-tco-model-data.

RECENT/RELATED RESEARCH

Jobs & Our Economy
Inflation in the Midwest – October 2026
All the data referenced in this report come from the U.S. Bureau of Labor Statistics’ Consumer Price Index (CPI) database.…

November 10, 2026


Stepan Mysko
Infrastructure
The Tax Impact of Data Centers in Iowa: New Revenue for Communities, Relief for Taxpayers
Introduction Iowa’s data center sector has grown from a handful of campuses into one of the fastest-growing parts of the…
Infrastructure
The Economic Impact of Data Centers in Iowa
Introduction Critics often argue that data centers bring large buildings and heavy power demand but few jobs, and on its…
Jobs & Our Economy
Iowa Jobs and Labor Force Update – September 2026
Summary Iowa added 1,800 nonfarm jobs in September, with private-sector employment rising by 400 and government employment rising by 1,400.…

October 20, 2026


Stepan Mysko