October 8, 2026
Experts:
Ballot Issue 7A: Proposed Tax for Front Range Rail
Key Findings
The proposed sales tax would reach many residents without nearby station access.
- CSI estimates that roughly 900,000 district residents, about one-third of the population, live more than five miles from any planned station.
FasTracks, Colorado’s last major effort to expand passenger rail, remains unfinished nine years after its planned 2017 completion, with costs substantially above initial estimates.
- By 2024, only 78 of the 119 planned rail miles had been built at an average cost of $72 million per mile, compared with the original $40 million estimate.
- In February 2026, RTD leadership signaled that the project would never be finished.
Ballot Issue 7A would impose a permanent tax generating substantially more revenue than projected annual operating costs.
- At $295 million annually, 15 years of tax revenue would equal the estimated $4.4 billion construction cost of expanded service.
- After construction, the tax would continue collecting revenue projected to grow beyond $295 million annually, compared with estimated tax-funded operating costs of $55–80 million for expanded service.
Projected ridership would replace less than 0.3% of annual vehicle travel along I-25 between Pueblo and Fort Collins.
- Assuming average trips of 40 miles, CSI estimates 20.5 million vehicle-miles replaced annually, compared with 6.9 billion corridor vehicle-miles in 2024.
The proposed sales tax is projected to reduce statewide economic activity, even after accounting for new transit spending.
- CSI’s model projects 417 fewer jobs and cumulative losses of $1.23 billion in GDP and $528 million in personal income through 2036.
- Affected municipalities would move up an average of 14 places in Colorado’s sales-tax ranking, including Denver from 26th to 14th and Boulder from 25th to 10th.
The Colorado Connector would serve a smaller population than all nine comparable rail networks identified by FRPRD.
- Eight of those networks reported operating losses in FY2025, and none exceeded 60% average seat utilization.
Ballot Issue 7A and the Colorado Connector
The appeal of intercity rail in Colorado faces a momentous test on Election Day, when residents of the 12-county Front Range Passenger Rail District (FRPRD) will be asked to balance the merits of a southward extension to the planned Colorado Connector, set at present for deployment between Denver and Fort Collins, against a permanent tax hike. The proceeds of this levy, a 0.333 percentage-point increase of all local sales-tax rates within the district, would fund the inception and eventual operation of eight daily round-trips from Denver to a new southern terminus in Pueblo, visiting the metro area’s southern suburbs and Colorado Springs along the way. This would raise affected cities’ total rates as high as 9.538% and cause them to ascend the ranking of Colorado’s highest local sales taxes by an average of 14 places (see the appendix for data on all 31 FRPRD municipalities).
| Municipality | Current sales tax | Statewide rank | Total after 7A |
Rank after 7A | Rank change (places gained) |
| Boulder | 9.195% | 25 | 9.528% | 10 | 15 |
| Denver | 9.150% | 26 | 9.483% | 14 | 12 |
| Fort Collins | 8.300% | 65 | 8.633% | 56 | 9 |
| Colorado Springs | 8.200% | 68 | 8.533% | 59 | 9 |
| Pueblo | 7.600% | 135 | 7.933% | 97 | 38 |
| Lakewood | 7.500% | 137 | 7.833% | 125 | 12 |
| Centennial | 6.750% | 189 | 7.083% | 155 | 34 |
This will not be the first time the Colorado Connector, approved earlier this year for its first phase of deployment, has confronted popular scrutiny. Debate over transportation patterns, fiscal prudence, and cultural particularity colors the project’s long-standing controversy, which pits supporters seeking an elegant cure for civic issues along the I-25 corridor against skeptics unconvinced of its potential beyond that of a turgid, ill-fated vanity project. It is the first time, however, that voters will exert direct influence over the plan: the outcome of Ballot Issue 7A, which would raise $295 million per year and authorize $580 million in debt through a new sales tax, will dictate much about the future of passenger rail in the region. This report models the economic impact of the proposed tax and offers the following observations, based on evidence from Colorado and elsewhere, about Ballot Issue 7A and the utility of intercity rail along the Front Range.
The tax outreaches the service
Disregarding its full economic effects, which will precipitate throughout all of Colorado, the proposed new sales tax reaches beyond the Colorado Connector’s territory in two principal ways: by applying to areas several miles away from any station and by taxing visitors to, not just residents of, the affected cities.
The dimensions of the FRPRD are designed to include municipalities at least 20% of whose populations live within five straight-line miles of a proposed station.[i][ii] Although as much as 85% of the state population resides within five miles of the Colorado Connector’s tracks, according to engineering-consulting firm WSP, CSI analysis of Census geospatial data estimates that only about two-thirds of the FRPRD’s population lives within that distance of any planned station.[iii][iv] This means that roughly 900,000 residents of the region encompassed by the new tax live outside of the project’s five-mile range. Nothing precludes some ridership coming from outside these circles, but neither should planners expect that those who live merely four or five miles away from a station necessarily find any convenience in the service.
Besides covering areas that lack close access to the Colorado Connector, the proposed tax would also impact consumers who live outside of the district. Businesses in hubs across the Front Range, like downtown areas of the state’s biggest cities and popular suburban malls like Colorado Mills, attract shoppers from outside their respective municipalities and tourists from other states altogether. These visitors, when purchasing taxable goods within the district, would pay higher prices without receiving the benefits of proximity to the new trains. This could suppress commerce within the affected boundaries and cause injury to local businesses, many of which already suffer under high urban tax rates and regulatory burdens.
Local conditions disfavor passenger rail
The Colorado Connector’s Delivery Plan identifies nine comparable passenger-rail networks across the country, all but one of which operate at losses despite serving larger populations than the proposed Colorado line.[v][vi] No comparable network fills more than 60% of its available seats, on average.
| Populations Served by Comparable Intercity Rail Networks | |||
| Total population of metropolitan areas served | FY25 adjusted operating earnings | Average utilization | |
| Amtrak Cascades | 11.54 million[1] | -$17,800,000 | 56.9% |
| Capitol Corridor | 9.55 million | -$8,900,000 | 30% |
| Carolinian/Piedmont (NC core) | 6.15 million | -$7,300,000 | 59.5% |
| Downeaster | 5.61 million | -$5,600,000 | 36.2% |
| Hiawatha | 11.01 million | -$200,000 | 50.7% |
| Lincoln Service | 12.63 million | $300,000 | 53.3% |
| Pacific Surfliner | 17.68 million | -$13,800,000 | 27.6% |
| Gold Runner | 11.07 million | -$6,700,000 | 23.7% |
| Wolverine | 14.90 million | -$9,600,000 | 57.3% |
| Colorado Connector | 4.75 million | N/A | N/A |
State-sponsored intercity rail in the United States tends to perform best when it links multiple large cities through densely populated corridors. Whether or not Ballot Issue 7A passes and the Colorado Connector expands to Pueblo, Colorado’s rail network will become only the second of the 10 listed systems to not pass through any two of the country’s 50 biggest metropolitan areas. The other, the Downeaster between Boston and Portland, ME, recorded a $5.6 million operating loss and less than 40% utilization in 2025 despite connecting a 5,000,000-resident metropolitan area to a major tourism route. Given published assumptions about Colorado Connector ridership and an average one-way trip distance of around 40 miles, its utilization rate could settle below 15%.[2] If the average trip distance reaches 60 miles, nearly the full distance between Denver and Fort Collins, utilization would be around 21%.
Subsidized transit often fails its mandate
Mass transit routinely comes under criticism for abusing public funding; recent data from the Federal Transit Administration do little to help repair that reputation. Between 2019 and 2024, the latest year for which data are available, passenger miles taken on public transportation fell by 29.8% across the country while inflation-adjusted operating and administrative spending by transit systems rose by 5.4% and 26.2%, respectively.[vii] Even before 2019, ridership was in decline while real spending levels grew. Now that COVID-19’s disruptions have ended, ridership looks as though it may never recover to its pre-pandemic standard.
RTD, the largest public-transportation system in Colorado, has underperformed even the national average. Its ridership has fallen by 38.4% since 2019, its real operating and administrative spending have risen by 12.9% and 34.4%, and previous CSI research finds that it faces other problems of cost, ridership, and safety.[viii] In 2025, there were 95 reported assaults on RTD transit, and the system is currently on pace for 93 in 2026.[ix]
Trains will not fix commutes
One of the Colorado Connector’s stated purposes is to reduce vehicle traffic within and between the cities of the Front Range, especially along the notoriously congested I-25 corridor. Its capacity to achieve this, according to the project’s own assumptions, is negligible. At full operation, including the proposed service to Pueblo, trains are expected to carry 3,500 passenger-trips per day, according to the Delivery Plan. Passenger surveys of six Amtrak routes, five of which are among the nine comparable lines above, find that a simple average of 61% of rail trips would be made by car in the absence of those routes.[x] At an average vehicle occupancy of 1.52, this means that the Colorado Connector can expect to replace 1,405 daily, and 512,825 yearly, vehicle trips along the I-25 corridor.[xi] If these trips average 40 miles, the Colorado Connector will displace 20.5 million vehicle-miles per year—less than 0.3% of the 6.9 billion driven anywhere on I-25 between Pueblo and Fort Collins in 2024.[xii] Much of this displacement would not occur during rush hours given surveyed ridership patterns; whether the project will consistently reduce commuting times at all is uncertain given the trains’ extensive use of grade crossings in urban environments.
The total capital cost to build and expand the Colorado Connector is projected to approach $4.7 billion through 20 years. At the costs of previous transportation projects, a similar amount of money could fund widening I-25 by two lanes across its entire 170-mile length between Fort Collins and Pueblo or quadrupling the statewide fleet of public-transit buses.[xiii][xiv] Both alternatives would likely relieve congestion more efficiently than a low-utilization rail line that does not guarantee faster commuting times than those possible by car.
Expansion would precede launch
Voters are being asked to fund several phases of expansion to a project that won’t have come into service at the time of asking. Such a proposition might be better received after the first phase, the line from Denver to Fort Collins, proves its worth to riders, especially because there are reasons to question whether it will. Ambitious transit projects like the Colorado Connector frequently overrun their initial timelines and budgets, even on local precedent: FasTracks, a major expansion of RTD’s light rail network in the Denver area, was approved in 2004 for completion in 2017 at a cost of $40 million per rail-mile; by 2024, only 78 of its 119 planned miles had been built and at an average cost of $72 million per mile. The FasTracks expansion was funded by a 0.4% local sales tax, very near the 0.333% tax designed to fund the Colorado Connector, and may never be completed.[xv]
Arguably, overspending is a fundamental expectation behind Ballot Issue 7A, which proposes a permanent $295,000,000-per-year tax hike despite published capital- and operating-cost estimates of $1.7 billion over six years of construction and just $15 million[3] per operational year for expanded service to Pueblo. If the project fulfills these expectations, annual revenue will exceed its funding of operations by almost 20 times. The Delivery Plan explains that the excess revenue would fund yet more distant future network expansions; even if every such expansion goes according to plan, despite demand for passenger rail that decreases with distance from Denver and its neighboring cities, $295 million will still exceed projected long-term operating costs by around 300%.
A new tax would hurt the economy
Ballot Issue 7A’s reasons for raising taxes are not strictly economic in nature, but a new sales tax would damage the local economies it affects. According to a simulation in REMI’s Tax-PI economic model, a $295 million increase in sales taxes alongside an equal investment in public passenger transit would cause permanent losses in employment, GDP, output, and personal income across Colorado.
| Economic Impacts of Ballot Issue 7A through 2036 | |
| Employment | -417 |
| Cumulative GDP | -$1,228,000,000 |
| Cumulative output | -$1,404,000,000 |
| Cumulative personal income | -$528,000,000 |
Conclusion
If the Colorado Connector is to deliver on its promises of reduced road congestion, greater urban interconnection, and economic vitality, it will need to overcome the threats of low demand, excessive costs, and concentrated economic harm within the areas it serves. Voters should consider the full costs of Ballot Issue 7A, including the risks of funding an unproven service, and weigh them against the benefits they expect to receive.
Appendix: Sales Tax Rates in 31 FRPRD Municipalities
| Municipality | State | County | RTD | SCFD | Transit | City | Total | Statewide rank | Total after 7A |
Rank after 7A | Rank change (places gained) |
| Lafayette | 2.900% | 1.335% | 1.000% | 0.100% | 0.000% | 3.870% | 9.205% | 22 | 9.538% | 9 | 13 |
| Boulder | 2.900% | 1.335% | 1.000% | 0.100% | 0.000% | 3.860% | 9.195% | 25 | 9.528% | 10 | 15 |
| Denver | 2.900% | 0.000% | 1.000% | 0.100% | 0.000% | 5.150% | 9.150% | 26 | 9.483% | 14 | 12 |
| Louisville | 2.900% | 1.335% | 1.000% | 0.100% | 0.000% | 3.775% | 9.110% | 27 | 9.443% | 18 | 9 |
| Superior | 2.900% | 1.335% | 1.000% | 0.100% | 0.000% | 3.775% | 9.110% | 27 | 9.443% | 18 | 9 |
| Manitou Springs | 2.900% | 1.230% | 0.000% | 0.000% | 1.000% | 3.900% | 9.030% | 31 | 9.363% | 26 | 5 |
| Westminster | 2.900% | 0.750% | 1.000% | 0.100% | 0.000% | 4.250% | 9.000% | 32 | 9.333% | 27 | 5 |
| Longmont | 2.900% | 1.335% | 1.000% | 0.100% | 0.000% | 3.530% | 8.865% | 47 | 9.198% | 31 | 16 |
| Federal Heights | 2.900% | 0.750% | 1.000% | 0.100% | 0.000% | 4.000% | 8.750% | 50 | 9.083% | 33 | 17 |
| Mountain View | 2.900% | 0.500% | 1.000% | 0.100% | 0.000% | 4.000% | 8.500% | 56 | 8.833% | 51 | 5 |
| Trinidad | 2.900% | 1.500% | 0.000% | 0.000% | 0.000% | 4.000% | 8.400% | 61 | 8.733% | 53 | 8 |
| Fort Collins | 2.900% | 1.050% | 0.000% | 0.000% | 0.000% | 4.350% | 8.300% | 65 | 8.633% | 56 | 9 |
| Colorado Springs | 2.900% | 1.230% | 0.000% | 0.000% | 1.000% | 3.070% | 8.200% | 68 | 8.533% | 59 | 9 |
| Broomfield | 2.900% | 0.000% | 1.000% | 0.100% | 0.000% | 4.150% | 8.150% | 76 | 8.483% | 63 | 13 |
| Englewood | 2.900% | 0.250% | 1.000% | 0.100% | 0.000% | 3.800% | 8.050% | 85 | 8.383% | 67 | 18 |
| Edgewater | 2.900% | 0.500% | 1.000% | 0.100% | 0.000% | 3.500% | 8.000% | 88 | 8.333% | 70 | 18 |
| Glendale | 2.900% | 0.250% | 1.000% | 0.100% | 0.000% | 3.750% | 8.000% | 88 | 8.333% | 70 | 18 |
| Littleton | 2.900% | 0.250% | 1.000% | 0.100% | 0.000% | 3.750% | 8.000% | 88 | 8.333% | 70 | 18 |
| Wheat Ridge | 2.900% | 0.500% | 1.000% | 0.100% | 0.000% | 3.500% | 8.000% | 88 | 8.333% | 70 | 18 |
| Arvada | 2.900% | 0.500% | 1.000% | 0.100% | 0.000% | 3.460% | 7.960% | 93 | 8.293% | 72 | 21 |
| Cherry Hills Village | 2.900% | 0.250% | 1.000% | 0.100% | 0.000% | 3.500% | 7.750% | 123 | 8.083% | 90 | 33 |
| Sheridan | 2.900% | 0.250% | 1.000% | 0.100% | 0.000% | 3.500% | 7.750% | 123 | 8.083% | 90 | 33 |
| Pueblo | 2.900% | 1.000% | 0.000% | 0.000% | 0.000% | 3.700% | 7.600% | 135 | 7.933% | 97 | 38 |
| Lakewood | 2.900% | 0.500% | 1.000% | 0.100% | 0.000% | 3.000% | 7.500% | 137 | 7.833% | 125 | 12 |
| Lakeside | 2.900% | 0.500% | 1.000% | 0.100% | 0.000% | 2.800% | 7.300% | 148 | 7.633% | 136 | 12 |
| Columbine Valley | 2.900% | 0.250% | 1.000% | 0.100% | 0.000% | 3.000% | 7.250% | 149 | 7.583% | 138 | 11 |
| Greenwood Village | 2.900% | 0.250% | 1.000% | 0.100% | 0.000% | 3.000% | 7.250% | 149 | 7.583% | 138 | 11 |
| Loveland | 2.900% | 1.050% | 0.000% | 0.000% | 0.000% | 3.000% | 6.950% | 157 | 7.283% | 151 | 6 |
| Centennial | 2.900% | 0.250% | 1.000% | 0.100% | 0.000% | 2.500% | 6.750% | 189 | 7.083% | 155 | 34 |
| Starkville | 2.900% | 1.500% | 0.000% | 0.000% | 0.000% | 0.000% | 4.400% | 234 | 4.733% | 234 | 0 |
| Bow Mar | 2.900% | 0.250% | 1.000% | 0.100% | 0.000% | 0.000% | 4.250% | 235 | 4.583% | 235 | 0 |
[1] Includes Vancouver, BC
[2] 3,500 daily trips, 10 round-trips north of Denver and 8 south of Denver, and 300+ seats per train; 70% of all trips are expected to occur along the northern 69 track miles (including much shorter intermediate trips, for example to Boulder or the northern Denver suburbs) between Denver and Fort Collins while only 5% are expected to span the full ~190 miles to Pueblo, making 40 average miles per one-way trip a reasonable possibility
[3] The full operating cost is listed at up to $51 million, just $10–15 million of which would be funded by revenue from 7A.
[i] https://www.kktv.com/2026/08/28/rail-district-board-votes-refer-colorado-connector-funding-measure-ballot/
[ii] https://www.cbsnews.com/colorado/news/colorado-front-range-passenger-rail-name-vote-results/?intcid=CNR-02-0623
[iii] https://www.wsp.com/en-us/insights/2025-utah-frontlines-transit-model-for-other-initiatives
[iv] https://services.arcgis.com/P3ePLMYs2RVChkJx/ArcGIS/rest/services/USA_Census_Block_Points/FeatureServer/0
[v] https://coloradoconnector.com/wp-content/uploads/2026/08/Delivery-Plan-Colorado-Connector-August-31-2026-Final.pdf
[vi] https://www.amtrak.com/content/dam/projects/dotcom/english/public/documents/corporate/monthlyperformancereports/2025/Amtrak-Monthly-Performance-Report-September-2025.pdf
[vii] https://www.transit.dot.gov/ntd/data-product/ts22-service-data-and-operating-expenses-time-series-system-0
[viii] https://commonsenseinstituteus.org/colorado/research/infrastructure/fork-in-the-railroad/
[x] https://utcm.tti.tamu.edu/publications/final_reports/Morgan_11-10-75.pdf?utm_source=chatgpt.com
[xi] https://www.fhwa.dot.gov/policyinformation/nhstable.cfm
[xii] Analysis of AADT and segment length: https://data-cdot.opendata.arcgis.com/datasets/cdot::highway-traffic-all-years/explore?layer=0&location=39.643447%2C-104.763420%2C10
[xiii] https://www.codot.gov/projects/archives/i25southgap and https://www.codot.gov/programs/ctio/assets/hpte-annual-reports-1/annual-and-legislative/ctio-2024-annual-report-draft-v5.pdf; reported construction costs per mile scaled to 170 miles establish a range of about $4 to $6 billion
[xiv] fleet size: https://www.transit.dot.gov/ntd/data-product/2024-vehicles; prices: https://cdn.rtd-denver.com/image/upload/v1734383703/FFTP-FTA-Transition-Plan_2024-12-16_hbflpy.pdf
[xv] https://www.cpr.org/2026/02/11/rtd-fastracks-funding-comments/